Section-1 Ground jumper check for Model 941, 94E

Procedure

  1. Verify that a yellow and green ground jumper Callout label 1 is installed between each primary power supply (PPS) and the frame. See Figure 1
    Note: There should be a star washer between the ground jumper terminals at the frame and PPS.
    Figure 1. PPS ground strap
    PPS ground strap
  2. Verify that the ground jumpers are installed between each battery module enclosure and the frame Callout label 2. See Figure 2.
    Note: There should be a star washer between the ground jumper terminals at the frame and enclosure.
    Figure 2. Ground straps
    Ground straps
  3. Verify that the ground jumper is installed between the 208V distribution assembly and the frame Callout label 1. See Figure 2.
  4. Complete the safety inspection by going to Safety engineering changes.

Section-2 Ground jumper check for Model 951, 95E

Procedure

  1. Verify that a yellow and green ground jumper Callout label 1 is installed between each primary power supply (PPS) and the frame. See Figure 3.
    Note: There should be a star washer between the ground jumper terminals at the frame and PPS.
    Figure 3. DC-UPS ground strap
    DC-UPS ground strap
  2. Verify that the yellow and green ground jumpers Callout label 2are installed between each PDU and frame. See Figure 3.
    Note: There should be a star washer between the ground jumper terminals at the frame and enclosure.
  3. Complete the safety inspection by going to Safety engineering changes.

Section-3 Ground jumper check for Model 961, 96E

Procedure

  1. Verify that a yellow and green ground jumper Callout label 1 is installed between each DC-UPS and the frame. See Figure 4.
    Note: There should be a star washer between the ground jumper terminals at the frame and enclosure.
    Figure 4. DC-UPS ground strap
    DC-UPS ground strap
  2. Verify that the yellow and green ground jumpers Callout label 2 are installed between each PDU and frame. See Figure 4.
    Note: There should be a star washer between the ground jumper terminals at the frame and enclosure.
  3. Complete the safety inspection by going to Safety engineering changes.